The pipework for the underfloor heating has now been laid. Now we just have to hope that one day we'll be able to afford the boiler or heat pump to run it off... I like to think of it as future-proofing. You can see a gap in the pipe work closest to us - that is for the fitting between the lounge and the library, and also where the fireplace will go.
That big void in the middle is the stairwell. You can also see the steel reinforcing on the tray deck. Since this was taken on Saturday, some more plumbing has been put in and the rebates have been done for all doors in the area. Which means that we're now ready for concrete!
The pour is tentatively scheduled for 9 am tomorrow (Tuesday), but so is the rain.... The combination could spell disaster.
This other photo is just a random, arty one. It looks more arty on the big screen!